From accepted estimate to move-in ready. Two months of contract, eight to twelve months of build.

New construction timeline

Timeline Summary

Contract2 months6 weeks if cashBuild8–12 monthsTotal10–14 months
M1M2M3M4M5M6M7M8M9M10M11M12M13M14
Part oneContract & Design
Part twoBuild
Cash closing
Certificate of occupancy window · months 11–14
AcceptedPrice and scope agreed, contracts begin.
Closing on the landThe lot is yours. Ground breaks, and construction begins.
Certificate of occupancySigned off, cleaned, keys in hand.
Part one · 2 months

Contract

Diligence runs in parallel. Expect about eight weeks from a signed estimate to clear to close on a financed purchase.

WK 1WK 2WK 3WK 4WK 5WK 6WK 7WK 8
01 Accepted estimate Price and scope agreed. The clock starts.
Day 1
02 Attorneys review contract Both sides’ counsel work the paper.
2 weeks
03 Contract signed Fully executed and delivered.
Week 2
04 Title ordered → cleared Ordered early, cleared by week seven.
3 weeks
05 Survey ordered → received Boundaries and setbacks confirmed.
3 weeks
06 Architectural plans ordered Drawings begin while diligence runs.
3 weeks
07 Financing started Application, underwriting, commitment.
6 weeks
08 Appraisal ordered Ordered once underwriting opens.
4 weeks
09 Clear to close Lender or attorney conditions satisfied.
Week 7
10 Closing on the land The lot is yours. Ground breaks next.
Week 8
Showroom, fixtures & finish selections.
Part two · 8–12 months

Build

The land is yours from day one of this phase. Twelve months is the outside — many homes finish in eight to ten.

M1M2M3M4M5M6M7M8M9M10M11M12
11 Foundation & drainage Excavation, footings, waterproofing.
2 months
12 Framing & roof The house takes its shape and gets dry.
2 months
13 Plumbing, electric & HVAC rough-in, pool rough, septic Everything behind the walls goes in.
3 months
14 Insulation, drywall & spackle Rooms become rooms.
2 months
15 Paint & flooring, finish carpentry Your selections land on site.
1 month
16 Pool final, punch list & touch-ups The last five percent, done properly.
1 month
17 Final inspection & C/O Signed off, cleaned, keys in hand.
1 month

Durations are typical and run in parallel where shown. Weather, materials availability, municipal review, lender delays, and selection changes can move dates; your project manager will always communicate with you about any unexpected delays and implications.

A Rustic Pines chalet in the forest
Get in touch

Learn more, get custom pricing, or schedule your tour today.

Or call / text us at (845) 209-1834.

Zev Eisenberg & Sheneur Menaker Home Designers & Sales Agents